2016, vol. 14, br. 1, str. 121-127
Metod ocenjivanja sposobnosti završavanja građevinskog projekta do utvrđenog datuma i kontrola kvaliteta
aSaint Petersburg State Polytechnical University, Saint Petersburg, Russia
bState Regional Centre for Standardization, Metrology and Testing, Saint Petersburg, Russia
cMagadan Institute of Economics, Saint Petersburg, Russia

e-adresabovteev@bk.ru
Ključne reči: Planiranje; Upravljanje projektima; Indeksi performanse; Performanse projekta
Sažetak
U radu se rasmatraju principi obezbeđivanja završavanja građevinskih projekata do utvrđenog datuma. Predložena metodika ocenjivanja progresa projekta i ocenjivanja mogućnosti svojevremenog završetka projekta, osnovana je na primeni pokazatelja ScheduleTimelessIndex (STI) i ScheduleProgressIndex (SPI). Metodika dozvoljava dinamično analiziranje otstupanje rokova projekta za operativno donošenje efektivnih upravljačkih rešenja.
Reference
*** (2012) Project management body of knowledge. Newtown Square, Pennsylvania: Project Management Institute, 5th ed
*** Project management in construction. Fourth Edition, pp. 285
Archibald, R.D. (2003) Managing High-Technology Programs and Projects. p. 396; 3rd Edition
Bovteev, S., Terentieva, E. (2014) Construction project schedule control, Project and Program Management. No. 2, pp. 158-173
Chatfield, C., Johnson, T. (2013) Microsoft Project 2013. Step by step. Washington: Redmond
Chegotova, E.V. (2012) The Role of techni- cal customer in the organization of invest- ment activities in construction. Magazine of Civil Engineering, 29(3), pp. 5-11
Ćetković, J., Rutešić, S., Žarković, M., Knežević, M., Vatin, N. (2015) Primary Directions and Advancements in Competitiveness of Montenegrin Construction Sector. Procedia Engineering, 117: 775-785
Ćetković, J., Knežević, M., Žarković, M., Murgul, V., Vatin, N. (2014) Development and Competitiveness Improvement of the Construction Sector in Montenegro. Applied Mechanics and Materials, 638-640: 2465-2470
Heldman, K. (2009) PMP: Project Management Professional Exam study Guide. Ministarstvo poljoprivrede NR Srbije, p. 677; 5th Edition
Homutinnikova, K.C. (2009) Evaluation Cri- teria methods of verification used in manag- ing construction projects. Management projects and programs, No. 4, pp. 312-323
ICB - IPMA Competence Baseline (2006) Version 3. O. Nijkerk, The Netherlands
Lipke, W. (2012) Earned schedule contribution to project management. PM World Journal, Vol. 1, Issue 2
Lynch, L. (2010) On Time and under budget: A project management method critical chain. pp. 354
Ptukhina, I.S. (2011) Methodology of the distribution of economic justice the perpetra- tors for the delay of completion. Kuban state agrarian University, 04(68), pp. 383-394
Pukhkal, V., Murgul, V., Garifullin, M. (2015) Reconstruction of Buildings with a Superstructure Mansard: Options to Reduce Energy Intensity of Buildings. Procedia Engineering, 117: 624-627
Rutešić, S., Ćetković, J., Knežević, M., Žarković, M., Vatin, N. (2015) Institutional Framework, Current Investments and Future Strategic Direction for Development of Construction Sector in Montenegro. Procedia Engineering, 117: 637-645
Rutešić, S., Ćetković, J., Žarković, M., Knežević, M., Vatin, N. (2015) Analysis of the Situation in Montenegrin Civil Engineering Sector from the Point of Application of National Regulations and the EU Technical Standards in Construction. Procedia Engineering, 117: 900-910
Schlagbauer, D., Heck, D. (2013) Change in output performance due to prolonged work. u: ISEC 2013 - 7th international structural engineering and construction conference: New developments in structural engineering and construction, pp. 1375-1380
Suetin, S.N., Titov, S.A. (2014) Project port- folio management: strategic level of project management. Economy and Entrepreneurship, 5-2 (46-2), pp. 509-515
Vatin, N.I., Kolosova, N.B., Berdyugin, I.A. (2013) Efficiency of application of automatic control systems, accugrade in construction. Construction of Unique Buildings and Structures, 4 (9), pp. 29-35
Werkl, M., Heck, D. (2011) Coping with incompleteness: An approach using time and production related compensation. u: ISEC - 6th International Structural Engineering and Construction Conference: Modern Methods and Advances in Structural Engineering and Construction, pp. 279-284
Williams, D.L., Krazer, E.B. (2012) Oracle Primavera P6 Version 8: Project and Portfolio Management. Birmingham - Mumbai: PACKT Publishing, A comprehensive Guide to managing projects, resources, and portfolios using Primavera P6, through version 8. 2
Yakovlev, Y.V. (2010) Mechanisms of management of complex investment and construction project. Moscow: Creative house
Yu, N. (2008) Lapygin Project management: from planning to evaluation. Moscow: Omega-L, p. 252
Zakieva, N.M., Sirazetdinov, R.M. (2011) Corporate project management system as management mechanism of innovative projects in investment-construction complex. News of the Kazan, No. 3, pp. 211-218
 

O članku

jezik rada: engleski
vrsta rada: izvorni naučni članak
DOI: 10.5937/jaes14-10443